Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 73095159 | Materials required for composting | Sanitation | 4350 | XV Finance Commission | Tied Grant | 2023-04-13 00:00:00 |
2 | 73096063 | Construction of Community Sanitary Complex | Sanitation | 75000 | XV Finance Commission | Tied Grant | 2023-06-14 00:00:00 |
3 | 73096686 | Computer | Rural electrification | 88000 | XV Finance Commission | Basic Grant (untied) | 2023-04-05 00:00:00 |
4 | 87011808 | Construction of Community Sanitary Complex | Sanitation | 70000 | XV Finance Commission | Tied Grant | 2023-07-13 00:00:00 |
5 | 87011853 | Materials required for composting | Sanitation | 7986 | XV Finance Commission | Tied Grant | 2023-06-12 00:00:00 |
6 | 106682860 | Drainage in Sannathi street in peroor pt | Roads | 188448 | XV Finance Commission | Basic Grant (untied) | 2024-02-06 00:00:00 |