S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 88000785 | Construction of Community Sanitary Complex | Sanitation | 488000 | XV Finance Commission | Tied Grant | 2023-09-07 00:00:00 |
2 | 88000869 | Construction of Community Sanitary Complex | Sanitation | 6000 | XV Finance Commission | Tied Grant | 2023-03-08 00:00:00 |
3 | 88000931 | Water Supply to villages | Drinking water | 493000 | XV Finance Commission | Tied Grant | 2023-09-13 00:00:00 |
4 | 88000970 | Water Supply to villages | Drinking water | 55586 | XV Finance Commission | Tied Grant | 2023-09-06 00:00:00 |