Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 59715053 | PURCHASE OF ELECTRICAL MATERIAL | Rural electrification | 150000 | XV Finance Commission | Basic Grant (untied) | 2023-09-22 00:00:00 |
2 | 59718777 | CONSTRUCTION OF CC DRAINS | Sanitation | 600000 | XV Finance Commission | Basic Grant (untied) | 2023-08-28 00:00:00 |
3 | 96875547 | Water Supply to villages | Drinking water | 1430000 | XV Finance Commission | Tied Grant | 2024-02-19 00:00:00 |
4 | 96875608 | Wages | Administrative & Technical Support | 600000 | XV Finance Commission | Basic Grant (untied) | 2024-02-13 00:00:00 |