Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 55772402 | Purchase of Hand bore Material and Purchase of Pipe line Materaial and Repair to Motors and other | Drinking water | 366887 | XV Finance Commission | Tied Grant | 2022-09-14 00:00:00 |
2 | 55772490 | Spl Repairs to CC Drains and Purchase of Sanitation Material | Sanitation | 366887 | XV Finance Commission | Tied Grant | 2022-11-09 00:00:00 |
3 | 55772701 | Purchase Of New Poles and New Electrical Line and Green Budget and Purchase of Computer | Rural electrification | 419182 | XV Finance Commission | Basic Grant (untied) | 2022-09-15 00:00:00 |