Physical Progress Report
S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 58176940 | Santitation | Sanitation | 80000 | XV Finance Commission | Tied Grant | 2022-12-28 00:00:00 |
2 | 58177461 | Sanitation | Sanitation | 72000 | XV Finance Commission | Tied Grant | 2023-04-11 00:00:00 |
3 | 58178158 | Drinking Water | Drinking water | 80000 | XV Finance Commission | Tied Grant | 2023-02-24 00:00:00 |
4 | 58178439 | Drinking Water | Drinking water | 72000 | XV Finance Commission | Tied Grant | 2022-12-15 00:00:00 |
5 | 58179082 | Electrification | Rural electrification | 115000 | XV Finance Commission | Basic Grant (untied) | 2023-01-19 00:00:00 |
6 | 58179414 | Sanitation | Sanitation | 30000 | XV Finance Commission | Basic Grant (untied) | 2022-11-21 00:00:00 |
7 | 58185426 | Drinking Water | Drinking water | 70400 | XV Finance Commission | Basic Grant (untied) | 2022-12-27 00:00:00 |