S.No | Activity Code | Activity Name | Focus Area | Admin Approved Cost(in INR) | Scheme Name | Component Name | Date of Completion |
---|---|---|---|---|---|---|---|
1 | 66434684 | construction of pucca path main road to ghameer chand house upper jakher | Roads | 126092 | XV Finance Commission | Basic Grant (untied) | 2023-01-19 00:00:00 |
2 | 66456493 | Construction of Community Sanitary Complex | Sanitation | 140569 | XV Finance Commission | Tied Grant | 2023-01-19 00:00:00 |
3 | 66456606 | repair road chil chagan se garlahn | Roads | 30000 | XV Finance Commission | Basic Grant (untied) | 2023-01-19 00:00:00 |
4 | 66468543 | Augmentation of the existing source of drinking water | Drinking water | 139569 | XV Finance Commission | Tied Grant | 2023-01-08 00:00:00 |